1. WAX INJECTION
 

The Process begins with production of a heat disposable pattern. This pattern is usually made by injecting wax into a metal die or mold. Pattern is injected in Horizontal Automatic Injection Machine. Water Cooling system is provided to reduce cycle time and to achieve dimension control of Pattern. For very close dimension control pattern resting guages also used.


2. PATTERN ASSEMBLY
 

The wax patterns are attached by the gate to a central wax runner system. The runner system is called a sprue. Patterns, runners, and pouring cup compromise the cluster or tree. Radius is provided to all joints between pattern and runner. Same checked thoroughly before coating to avoid rejection due to sand inclusions.

about
about
3. SHELL BUILDING
 

The shell building technique involves dipping the assembly into a ceramic slurry and then into a bed of extremely fine sand. After drying, the process is repeated. Up to 4 to 6 layers may be applied in this manner. All shell dried in Air Conditions in close range of temp. (22-26 C) & humidity. We also used Organic Fiber in secondary slurry bath to reduced cycle time and no. of coats. It also helps in improvement of permeability of shells.

4. DEWAX OPERATION
 

Completed shell is placed in a steam autoclave where the pattern melts and runs out through the gates and pouring cup. Auto clave dewaxing operation maintain quality of wax compare to convensonal dewaxing process.

about
about
5. SHELL PRE-HEATING
 

The ceramic shell molds must be fired to burn out the last traces of pattern material and to preheat the mold in preparation for casting, usually in the range of 800 to 1100 degrees centigrade. Amtech use rotary hearth furnesh with three burners which gives very much close control in shell temperature.

6. METAL POURING
 

The preheated shell is filled with molten metal by gravity pouring. As the metal cools, the parts, gates, sprue and pouring cup become one solid casting.

about
about
7. GATE/RISER CUTTING
 

After the metal solidifies and cools, the ceramic shell is then removed by vibratory methods or water blasting.

8. HEAT TREATMENT
 

Casting to be shot blasted to remove all small ceramic particles. Amtech also can supply casting with glass bead blasting or sand blasting if customer require.

about
about
9. SHOT BLASTING
 

Individual casting are removed from the cluster by means of a cut off wheel or weld cutting.

10. FINISHING OPERATION
 

Remaining gate protrusions are removed by belt grinding.

about
about
11. FINAL CASTING INSPECTION
 

Casting is Heat Treated as per specification in 1 tone capacity heat treatment furnace. Same has been calibrated as per standard APA 6 A.

12. MACHINING
 

Finally casting is dimensionally and visually inspected, packed as per customer specification and dispatched. Before dispatch all testing to be done like Die Penetrate Test, Magnetic Particle Test, Radiography Test etc. based on customer specification.